RENCANA  ANGGARAN  BIAYA (RAB)
DESA PASIR BERDENGUNG KECAMATAN PASIR LAUT
TAHUN ANGGARAN 2020
Bidang  : Pelaksanaan Pembangunan Desa (2)
Sub Bidang  : Pekerjaan Umum dan Penataan Ruang (2.3.)
Kegiatan  : Pembangunan Balai Kemasyarakatan (ii.3.fifteen.)
Pembangunan Balai Pertemuan RT. 1 RW. 2 Dusun Bahagia united kingdom. half dozen m x 12 m. 1 unit of measurement
Waktu Pelaksanaan  : 60 (enam puluh hari kalender)
Rincian Pendanaan  :
NO. U  R  A  I  A  Northward VOLUME HARGA SATUAN  (Rp) JUMLAH (Rp)
1 2 three four 5
I. BAHAN (harga hanya contoh)
1 Semen PC fifty Kg             72.00 Zak 90,000 6,480,000.00
two Semen Putih                 1.0 Kg 10,000 10,000.00
3 Pasir Beton             11.00 160,000 ane,760,000.00
4 Pasir Urug             22.00 120,000 two,640,000.00
5 Batu Pecah 2/iii Cm               iv.00 500,000 2,000,000.00
6 Batako Uk. 7 10 15 x 30 Cm           192.00 Bh 2,500 480,000.00
7 Keramik xx x twenty cm             12.00 Kotak 70,000 840,000.00
viii Kayu Belian 9/9-400 Cm             thirty.00 Btg 205,000 six,150,000.00
9 Kayu Belian 8/8-400 Cm             13.00 Btg 215,000 2,795,000.00
x Kayu Belian iv/eight – 400 Cm             12.00 Btg 103,000 i,236,000.00
xi Kayu Klas I eight/8 – 400 Cm             39.00 Btg 81,000 3,159,000.00
12 Kayu Klas I v/ten – 400 Cm               iv.00 Btg 75,000 300,000.00
13 Kayu Klas II 8/12 – 400 Cm             61.00 Btg 157,000 9,577,000.00
14 Kayu Klas 2 6/12 – 400 Cm             18.00 Btg 150,000 ii,700,000.00
15 Kayu Klas II 5/10 – 400 Cm               8.00 Btg 66,000 528,000.00
16 Kayu Klas 2 5/vii – 400 Cm             74.00 Btg 32,000 2,368,000.00
17 Kayu Klas 2 4/half dozen – 400 Cm             88.00 Btg 24,000 ii,112,000.00
18 Kayu Klas II ii/3 – 400 Cm             70.00 Btg 15,000 1,050,000.00
xix Papan Mall Klas III 2/18 – four g               9.00 Kpg 21,000 189,000.00
20 Papan Klas I Ketam 2/15 – iv k             40.00 Kpg 140,000 v,600,000.00
21 Alas Kayu Hutan iv/eight – 4 thou             12.00 Btg 46,000 552,000.00
22 Amplas             25.00 Lbr 5,000 125,000.00
23 Dempul             24.00 Kg 15,000 360,000.00
24 Cat Tembok             63.00 Kg xxx,000 1,890,000.00
25 Cat Kilat/Cat Minyak             13.00 Kg 75,000 975,000.00
26 Cat Dasar             10.00 Kg 25,000 250,000.00
27 Thinner               4.00 Ltr 27,000 108,000.00
28 Residu/Terr             x.00 Ltr 28,000 280,000.00
29 Kawat Simpai           212.00 Kg xx,000 4,240,000.00
xxx Besi Plat Beugel             25.00 Bh 20,000 500,000.00
31 Baut Bangunan           253.00 bh 5,000 i,265,000.00
32 Paku Campuran             51.00 Kg 22,000 ane,122,000.00
33 Paku Atap             15.00 Kg 25,000 375,000.00
34 Paku Triplek             16.00 Kg ten,000 160,000.00
35 Kunci Pintu               4.00 set 60,000 240,000.00
36 Engsel Pintu             15.00 set up 40,000 600,000.00
37 Engsel Jendela             32.00 ready l,000 1,600,000.00
38 Slot Jendela             32.00 set up ten,000 320,000.00
39 Kait Angin             32.00 set 10,000 320,000.00
twoscore Atap Seng Gelombang Warna           139.00 Lbr fourscore,000 xi,120,000.00
41 Seng Polos BJLS 0.30             xix.00 Lbr 60,000 one,140,000.00
42 Pintu Panel Kayu Belian               two.00 Bh 1,500,000 iii,000,000.00
43 Pintu Panel Kayu Klas I               iii.00 Bh i,000,000 3,000,000.00
44 Jendela Kaca Jungkit             16.00 Bh 350,000 5,600,000.00
45 Ventilasi             21.00 Bh 250,000 5,250,000.00
46 Triplek three mm             37.00 Bh 47,000 one,739,000.00
47 Kloset Jongkok               2.00 Bh 255,000 510,000.00
48 Kran Air               2.00 Bh 20,000 xl,000.00
49 Floordrain               2.00 Bh 35,000 lxx,000.00
50 Bak Air dalam WC               2.00 Bh 500,000 1,000,000.00
51 Pipa PVC 4″               ii.00 Btg 190,000 380,000.00
52 Pipa PVC 2″               4.00 Btg 85,000 340,000.00
53 Pipa Galvanis 2″               1.00 Btg 350,000 350,000.00
54 Lem Pralon               1.00 Bh x,000 10,000.00
55 Talang Air Fiber lengkap             ten.00 M
1
17,500 175,000.00
56 Fiber Glass Kap. 1 M3               ane.00 Bh 1,700,000 one,700,000.00
57 Sambungan Pipa               6.00 Bh 12,000 72,000.00
58 Stelling/ Menara Tandon Air               1.00 Bh ane,500,000 1,500,000.00
59 Pembuatan Septic Tank/Beerput               1.00 Bh ane,500,000 1,500,000.00
Jumlah Bahan 105,752,000.00
Two. SEWA ALAT
(sesuai keperluan)
i. Gerobak Dorong 4.00  Bh 200,000.00 800,000.00
Jumlah Alat 800,000.00
III. UPAH
1. Pekerja           133.00 HOK 85,000.00 eleven,305,000.00
ii. Tukang             99.00 HOK 120,000.00 xi,880,000.00
three. Kepala Tukang             44.00 HOK 140,000.00 6,160,000.00
4. Mandor             22.00 HOK 120,000.00 2,640,000.00
298.00 HOK Jumlah Upah 31,985,000.00
Iv. Laurels TPK
1. Ketua 1.00 org 450,000.00 450,000.00
ii. Sekretaris 1.00 org 400,000.00 400,000.00
iii. Anggota 2.00 org 350,000.00 700,000.00
(Perbup Sanggau No. 1 Thn. 2019)
4.00 org Jumlah Honor TPK 1,550,000.00
J  U  Chiliad  Fifty  A  H  (Rp.) 140,087,000.00
Pasir Bedengung, 28 Oktober 2019
Disetujui :
Kepala Desa Pasir Bedengung Kasi Kesejahteraan
Bunga Citra Lovestory, SH. Ramlee
Read:  Kalau Mau Membangun Rumah Apa Yang Fisiapkan

BACA JUGA : Desain dan RAB Balai Pertemuan 10m x 15m

Rab Pembangunan Rumah Bale Hinggil

Source: https://wiryocaram.blogspot.com/2019/10/desain-dan-rab-balai-pertemuan.html

You May Also Like